Philippine Construction Management SystemPRODUCTION SECURE
👨‍💼
Engr. Alexander MoralesSUPER
Managing Director & System Administrator
Category AAAA - General Engineering & BuildingBIR 2307 & RTWPB CompliantSuper Admin (Managing Director & System Administrator)

Skyline One Commercial Tower (7-Storey Office & Retail)

7th Avenue cor. 28th St., Bonifacio Global City, Taguig, Philippines•Client: Megaland Properties & Development Corp.•PM: Engr. Roberto Valenzuela (PM)
Quotation Award
₱68,500,000
Client Approved Baseline
Materials (BOM)
₱38,200,000
66% of Project Cost
Fleet & Hauling
₱5,400,000
9% Logistics Budget
Labor & Pakyaw
₱12,800,000
22% Direct Wages
Site Completion
42.5%Physical
On TrackQuotation-Based Earned Value Tracking

Project Health: Completion Rate vs. % of BOM Expenses Incurred

Validates if physical milestone accomplishments match the cumulative project expenses across materials, salaries, and heavy equipment.

42.5%
Drag to simulate progress
Physical Work Completed42.5%
Certified on-site structural works, casting, and framing accomplishment.
Running Expenses vs. Total BOM Budget12.4% (₱4,724,951)
Total cumulative cash disbursements divided by baseline BOM allowance (₱38,200,000).
Project Incurred Spend is Synchronized with Physical Progress

Site work completion (42.5%) is safely ahead of running expenditures (12.4% of BOM). Profit margin is protected.

Running Expenses by Direct Cost Category

Aggregated disbursements across materials, worker salaries, equipment rentals, and site incidentals.

1. Materials (BOM)

66%
₱3,743,500
Budget: ₱38,200,000

2. Worker Salaries & Pakyaw

22%
₱667,685
Budget: ₱12,800,000

3. Heavy Equipment & Fleet

9%
₱26,766
Budget: ₱5,400,000

4. Incidentals & Permits

3%
₱287,000
Budget: ₱1,500,000
Total Cumulative Running Expenses Disbursed₱4,724,951
Quotation Award:₱68,500,000
Target Gross Margin:₱10,600,000 (15.5%)
Remaining Cash Surplus:₱63,775,049

Recent Site Incidentals & Miscellaneous Expenses

Expense No & CategoryDescriptionDateReceipt / O.R.Approved ByAmount (PHP)
EXP-2026-041
Permits & Licenses
City Building Official Excavation & Heavy Equipment Lifting Permit Fee2026-08-15O.R. # 992144-TAGUIG-CBOEngr. Roberto Valenzuela (PM)₱85,000
EXP-2026-042
Testing & Inspection
Third-Party Laboratory Concrete Cylinder 7-Day & 28-Day Compressive Break Testing (DPWH Accredited)2026-09-02SI-55102-GEO-TESTEngr. Maria Santos (DPWH ME-1)₱45,000
EXP-2026-043
Safety PPE
Site Safety Helmets (Class E), High-Vis Vests, Fall Arrest Harnesses, and Steel-Toe Boots (50 sets)2026-08-20INV-4019-SAFETY-FIRSTEngr. D. Ramos (Site PE)₱125,000
EXP-2026-044
Site Petty Cash
Emergency generator diesel top-up & water utility installation for workers quarters2026-09-08PCV-2026-088Engr. Roberto Valenzuela (PM)₱32,000